Do you need a permit for an EV charger in San Francisco, CA?
It depends on the details of your project.
San Francisco requires an electrical permit for any new wiring, including a Level 2 charger.
Licensed contractors registered with the City can apply online.
Curbside chargers are shared public chargers installed by SFMTA-permitted vendors, not by homeowners.
A person last checked these rules on October 22, 2026. This is guidance only, so confirm with San Francisco before you build.
Check your exact lot
Your zoning district sets the setbacks, and a flood zone can change the permit answer. Enter your address to see both.
Permits a EV charger can need in San Francisco
| Permit | When it applies |
|---|---|
| Electrical permit | San Francisco requires an electrical permit for any new wiring. |
Local details
- Call 811 at least a few days before you dig footings or post holes. Utility locating is free.
- HOA covenants and deed restrictions can be stricter than city rules. Check yours before you build.
How to apply
- Check if your project needs a permit (sf.gov)
- SF Property Information Map
- Phone: (628) 652-3200
Common questions
- When does an EV charger need an electrical permit in San Francisco?
- San Francisco requires an electrical permit for any new wiring. Plugging a Level 1 cord into an outlet you already have needs no permit.
- Where do I apply for an EV charger permit in San Francisco?
- Apply through Check if your project needs a permit (sf.gov), or call (628) 652-3200.
Sources
- sf.gov, Apply for an electrical permit. Checked 2026-10-22
You need an electrical permit before installing new wiring or alterations, extensions, or additions [to existing electrical installations]... Only owner-installers of stand-alone single family dwellings may apply for an electrical permit to do the work them…